Home News

Completion date for repairs to £32m King’s Dyke bridge pushed back

John Elworthy by John Elworthy
10:26am, June 9 2023
in News
News for Peterborough - The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris

Cambridgeshire County Council says the movement of the embankment at the King’s Dyke bridge is being closely monitored and is currently showing that there is settlement of the embankment as well as horizontal movement “at a level greater than predicted at the design phase”.

Share on FacebookShare on Twitter

More work than was first thought necessary means contractors will not finish remedial work on the £32m King’s Dyke bridge, Whittlesey, until July.

Cambridgeshire County Council made the announcement of being contacted by CambsNews after we published photographs of the work in progress.

“The remedial work to the verge at the top of the embankment has been progressing well, although it has been necessary for the contractor to remove and replace material at a lower level than initially anticipated,” said a council spokesperson.

“The work has also been restricted by the availability of road space due to other works needing to take place in the area.

“We’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned.”

In April the council announced remedial work would begin on the bridge – known as Ralph Butcher Causeway – starting on 19 April for nine weeks “although we hope to finish sooner if possible”.

However, with the extra work now needed, the council has explained that the mid-June deadline has been extended to July.

“Following our post in April, we explained we were carrying out remedial work and at the end of any major scheme there is a period where final checks are completed,” said the spokesperson.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris
<br />Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

“Last year, there was a focus on Star Pit and a piled wall was installed below ground level.

“That work allowed the road’s embankment to be built on top.

“As part of that final check, Cambridgeshire County Council and Jones Bros agreed further work was required at the top of the embankment.”

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris
<br />Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

The spokesperson explained that the remedial work involves:

  • Removing the safety barrier and fence between the rail bridge and the underpass structures
  • Replacing the top 1.2m of verge
  • The installation of drainage
  • Reinstalling the safety barrier

“We’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned,” said the spokesperson.

Council dismisses visual ‘assessment’

The council has also dismissed a visual ‘assessment’ of the bridge made by an engineer who contacted CambsNews after seeing our recent photographs.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris
<br />Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

The engineer wrote: “From looking at the photos my guess is that once again the clever consultants have ignored the difficulties of building anything in Fenland with its very high-water table and poor ground stability.

Advertisements
canopyuk.com in-article

“They get this wrong every time despite the examples of the concrete guided busway at Impington, Fen Drayton and the piling needed to support the embankment on the Ely Southern Bypass.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris
The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris

“The views in the article quite clearly indicate that the work in hand is to stabilise the road embankment which appears to be visibly subsiding at one point. In other words, the underlying fen ground conditions will not support the weight of the concrete road structure and safety barrier.

“The whole lot appears to by migrating towards the excavated water filled pit at the right-hand side of the picture. You will note that where the road crosses the railway the Bridge abutments are deep piled to take the weight of the concrete span.

“The circular piles are clearly visible in the construction sequence still photos.

“One shudders to contemplate yet another legal action against the design and build contractors as the final product is clearly defective and unfit for purpose.”

 But his observations have been dismissed by the county council.

“As for the engineer comments – ‘the whole lot appears to be migrating’ this is not correct,” said the council spokesperson.

“Our monitoring records collected in the months before the remedial work started indicated that the carriageway was not affected.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris
<br />Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

“Hence why the material at the top of the verge is being replaced.

“The problem is believed to have occurred because the fill material originally used is not draining as expected.

“A different class of material is being used and a land drainage feature has also been included in replacement.”

The spokesperson also took issue with the observation that “the final product is clearly defective and unfit for purpose”.

The spokesperson said: “This is also not correct. We’re not sure what photos the engineer is commenting on, but the matter has been picked up as per our contract, it’s been investigated, further design work has been carried out and remedial work is being done to address it.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris
<br />Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

“The road won’t be fully completed until the contractor has completed all work, including remedial work, on site.

“The county council will be keeping the situation under review and if there are any further signs of movement following the reconstruction these will be followed up with the contractor in the normal way as per the contract.”

The spokesperson added: “We are carrying out the work as quickly as possible, and we thank everyone for their patience.”

 

 

Cathedral Shaun
Advertisements
Pictures

Advertisement
Tags: cambridgeshire county councilHomepagekings dykePeterboroughwhittlesey
ShareTweetSend
Next Post
News for Peterborough - Jail for Peterborough man caught growing £150,000 worth of cannabis plants

Jail for Peterborough man caught growing £150,000 worth of cannabis

News for Peterborough - A 625,000ft sq ft factory complex under construction in Peterborough is using a Bell 205A-1 Helicopter (Helilift Services) to move construction materials to the roof of the massive factory., Delta Park, Peterborough Saturday 10 June 2023. Picture by Terry Harris.

VIDEO: American ‘can do’ approach to £150m Peterborough factory

Help us by Donating

News for Peterborough -
News

Ralph Butcher Causeway: A Bridge Closed Longer Than It Has Been Open

June 9, 2025
News for Peterborough -
News

What went wrong with the Ralph Butcher Causeway? Councillor Update.

June 9, 2025
News for Peterborough -
News

Lifeline” Peterborough bus service threatened as Mayor refuses to rule out cuts 

June 5, 2025
News for Peterborough -
News

Traffic chaos on Frank Perkins Parkway

June 3, 2025
News for Peterborough -
News

Peterborough Regional Pool Nears Final Days as City Mulls Future Use of Site

June 2, 2025
News for Peterborough -
News

Tragic Accident: 18-Year-Old Man Killed in Car-Bus Collision

June 2, 2025
  • Trending
  • Comments
  • Latest
News for Peterborough - Police are appealing for witnesses and dashcam footage after a man died in a collision near Ely.

Owen Bird of March charged after A605 death crash which killed Peterborough man

December 27, 2024
News for Peterborough -

Threat to close £32m King’s Dyke crossing at Whittlesey if movement and cracking intensifies

October 18, 2024
News for Peterborough - Family and friends have paid tribute to talented musician Nick Smith of Peterborough whose death has been confirmed overnight. He was a member of Genesis Connected. PHOTO: Genesis Connected

Tributes to Peterborough musician Nick Smith of Genesis Connected

January 24, 2025
News for Peterborough -

VIDEO: Freight train hits Iceland delivery truck at March, Cambridgeshire

October 15, 2024
News for Peterborough -

High Flyer makes a ‘mug’ of planners

0

Town with unenviable crime record

0
News for Peterborough -

New owners of historic Cambridgeshire hotel bans sale of booze

0
News for Peterborough -

Child cruelty sentences for baby’s parents

0
News for Peterborough -

Ralph Butcher Causeway: A Bridge Closed Longer Than It Has Been Open

June 9, 2025
News for Peterborough -

What went wrong with the Ralph Butcher Causeway? Councillor Update.

June 9, 2025
News for Peterborough -

Lifeline” Peterborough bus service threatened as Mayor refuses to rule out cuts 

June 5, 2025
News for Peterborough -

Traffic chaos on Frank Perkins Parkway

June 3, 2025
News for Peterborough -
News

Ralph Butcher Causeway: A Bridge Closed Longer Than It Has Been Open

June 9, 2025
News for Peterborough -
News

What went wrong with the Ralph Butcher Causeway? Councillor Update.

June 9, 2025
News for Peterborough -
News

Lifeline” Peterborough bus service threatened as Mayor refuses to rule out cuts 

June 5, 2025
News for Peterborough -
News

Traffic chaos on Frank Perkins Parkway

June 3, 2025
News for Peterborough -
News

Peterborough Regional Pool Nears Final Days as City Mulls Future Use of Site

June 2, 2025
News for Peterborough -
News

Tragic Accident: 18-Year-Old Man Killed in Car-Bus Collision

June 2, 2025
  • News
  • Local Council
  • Investigations
  • Things To Do
  • Privacy Policy
  • Contact Us

© COPYRIGHT - UNIT 2 FENGATE TRADEPARK PETERBOROUGH PE15XB

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Add New Playlist

No Result
View All Result
  • 360 Examples
  • Advertise with us
  • ARTICLE FOOTER NOT FOR PUBLICATION
  • Basket
  • Beer Festival VR 360
  • Buy Adspace
  • Cambridgeshire
  • Cancel donation
  • Cathedral Example 360
  • Cathedral Plan
  • Checkout
  • Checkout
  • Complaints
  • Contact Us
  • Cookie Policy
  • cookie-policy
  • Elementor #420
  • Hide Ads for Premium Members
  • Home
    • CambsNews Live
  • Latest News
  • Media Consent Form
  • Memorial Garden Example
  • My Account
  • My account
  • Notices
  • Notices Form
  • Privacy Policy
  • PU test
  • Sample Page
  • Sample Page
  • Shop
  • SiteMap
  • Submit Your News
  • Support our work.
  • test2
  • Thank you for your donation
  • Upload your ads

© COPYRIGHT - UNIT 2 FENGATE TRADEPARK PETERBOROUGH PE15XB